What to ask your telematics provider, and how to turn the answer into a shortlist of first routes

7 min read

Most operators have a telematics contract. Very few have asked it the one question that matters for electrification: which of my trucks could go electric now, and what would they need to make it work?

That gap is everywhere. The RHA's March 2025 survey found 70% of operators had no plans to add zero emission vehicles. In our 12 Pillars workshops the same thing kept coming up. Operators had the data sitting in a portal they log into every day and had never pointed it at the question. One of the report's recommendations to operators was simply to interrogate the data they already have.

This guide covers what to ask for, what a good answer looks like and how to turn it into a shortlist. It's the cheapest bit of electrification work you'll ever do, and it belongs before the first conversation with a dealer.

What happened when we did it

In 2024 we loaded several months of tracking data from our tractor fleet into Dynamon's ZERO platform. It replayed our real diesel duties as if they'd been run on an electric Renault E-Tech T.

With charging only at home, one of our trunking tractors completed 48% of its journeys. Then we added a single 150kW charger at the Palletline hub in Birmingham, where our trucks already sit for hours every night. That went to 91%. A 250kW charger took it to 93%.

Same truck. Same routes. Same battery. One charger, in a place we already stop.

The trip-level numbers said the same thing. Bedford to Birmingham and back is 233 miles. The simulation used 480kWh against a 378kWh battery, so the truck came up 42kWh short, under 20 minutes on a 150kW charger. From Duxford the shortfall was 182kWh, and the truck sat at the hub for six hours.

Those numbers are from mid-2024. Ranges have gone up since and there's more charging about, so they're not a benchmark. They show the method working. The question was never whether the truck could do the route. It was where the truck already stops, and whether there's a charger there.

That changes what you ask for.

What to ask for

Ask for raw data, not a dashboard. You want one row per truck per day as a spreadsheet or CSV, covering at least twelve months so it includes a winter. A summer-only sample flatters everything.

For each truck, each day, ask for:

  • Total miles, with start and end location. You'll want the spread later, not the average.
  • Fuel used, so you can rank trucks by what they cost you.
  • Whether it came back to base that night, and how long it sat in the yard before going out again. That's your charging window.
  • Every stop over 30 minutes, with location and duration: customer sites, hubs, regular layovers. Trucks already wait 60 to 90 minutes at supermarket docks, and plenty of your stops will be longer than a top-up.
  • Gross weight or load data if the system records it, or a job reference you can match to your TMS.
  • Elevation or gradient on the route, if they can provide it.
  • The date, so you can split winter from summer.
  • Whether the truck was double-shifted, and when the drivers changed.

If your truck maker supplies the telematics, ask for rFMS access as well. It's the standard interface for truck data, and it means you can take the data to someone else's tool without asking permission every time.

Then ask how their tool decides where one duty ends and the next begins. When we first ran ours, any stop under five hours counted as part of the same duty. Our trucks run long days with short breaks, so a pile of duties got marked as failed for being too long and too far. Dropping the threshold to two and a half hours fixed most of it. If your provider's analysis says nothing works, check this before you believe it.

You might not need telematics at all

A first pass can come straight out of your TMS. Last year we ran one customer's delivery records through a basic range filter: delivery postcode, distance from our depot and two truck ranges.

With a truck that could cover 280km, 53% of their deliveries worked on depot charging alone and another quarter needed one top-up. With a 480km truck, 82% worked without charging and only 4% were out of reach. That took an afternoon and a spreadsheet. It also gave us something concrete to take into their contract renewal.

What good output looks like

A good answer is a table with one row per truck, showing:

  • median, 90th-percentile and worst-day daily miles
  • the share of days that fit a realistic winter range for the truck you're considering, with headroom
  • nights back at base
  • the longest regular stop away from base, and where it is
  • annual fuel spend
  • a verdict: works on depot charging, works with one top-up and where, or doesn't work yet

Distrust averages. A truck averaging 180 miles a day that does 320 twice a week isn't a 180-mile truck. The 90th percentile decides whether it works. The worst day decides what your plan B is.

Distrust assumed charging too. Most tools assume that if a truck stops at a site with a charger, it charges for the whole stop. In real life the bay's taken, the charger's the wrong power, or the driver's tipping for forty of the sixty minutes. Any top-up a duty depends on is a question to go and answer, not a done deal.

From table to shortlist

Filter first. Keep the trucks whose 90th-percentile day fits on depot charging, or fits with one top-up somewhere you control or have real influence over. We had that at Birmingham because Palletline is member-owned. Drop anything that relies on a public charger you've never seen.

Then rank by fuel spend. The truck burning the most diesel on a route electric can handle is the one that saves the most. Start there, not with the shortest route.

Then take the list to your planners. They'll tell you which trucks get swapped onto other work on a Thursday, which customer moves its delivery windows every quarter and which driver won't plug in. Twenty minutes with them saves months.

Last, check weight. Most work cubes out before it weighs out. Ours rarely weighs out at all. But a shortlisted truck that regularly runs at 44 tonnes needs a closer look, and our piece on payload and electric HGVs covers how.

You'll end up with a handful of trucks and a reason next to each. That's your first route.

Then work out the power

The same table tells you the energy you need each night. Add up the overnight kWh for the shortlist, divide by the hours they're parked, and you've got a rough figure for the kW you need at the depot. That's the number for your DNO, and for your landlord if you have one. If you lease, read depot charging on a leased yard before you go any further.

Do it before you order a truck. A depot connection takes 18 months to three years even when things go smoothly. A truck turns up in months.

Lean on depot charging wherever you can. Once public charging becomes a meaningful share of your energy, the cost case erodes quickly, so a shortlist that depends on public chargers is a weak one. The other lesson from Birmingham is that a top-up in the right place can be worth more than another charger at the depot. It turns half-working duties into whole ones.

Funding for trucks and chargers changes often. The current schemes are on our grant funding page.

The shortlist is already in your data. Someone just has to ask for it.