Depot charging on a leased yard

Sort the lease before you sort the chargers

5 min read

Most hauliers don't own their yard. That's fine for diesel. It becomes a problem the moment you want a charger, because you're about to sink twenty-five year kit into a site you might hold for five.

Sort the lease before you sort the chargers. Everything else follows from that.

At our Power In workshop the mismatch came up again and again. Typical commercial leases run five to fifteen years. Chargers, cabling, switchgear and substations are built to last twenty-five. A landlord who's paying attention knows the power you bring onto their site outlives your tenancy, and some are already pricing it in. One site discussed in the room had been quoted £35,000 a month with a defined supply capacity against £20,000 without it. One participant put it simply: "It used to be location, location, location, and now it's location, location, power."

What can go wrong

Reinstatement is the first trap. Most leases make you hand the site back as you found it. Read literally, that means paying to rip out chargers, cabling and switchgear at the end of the term. Kit that's worth more to the landlord in the ground than in a skip.

Ownership is the second. Anything fixed to the site can end up belonging to the landlord unless the lease says otherwise. Who owns the switchgear, and who controls the capacity behind it, matters more than who owns the charger heads.

Substations are the third. If you need one, you're dealing with three separate parties and three sets of paperwork: your lease with the landlord, the landlord's lease or easement to the DNO for the substation, and your connection agreement. Any one of them can stall the others.

Consent is the fourth. The Depot Charging Scheme needs landlord consent, needs a live connection agreement before you apply, and pays in arrears. A landlord who drags their feet costs you grant funding as well as time.

Then there's the grid queue. Since June 2026, applicants at 5 MVA and above have had to show secured land rights to hold their place, and Heads of Terms don't count. If you're taking on a new site and you're still at Heads of Terms, you can't use them to get in the queue. A sitting tenant with a signed lease is in a much stronger position than one still negotiating.

The good news on cost

The connection bill usually isn't as bad as the sector says. Since April 2023 the cost of wider network reinforcement for a distribution demand connection has been spread across all bill payers, up to a high-cost cap of £1,720 per kVA. What lands on you is mainly the sole-use assets: the cable and kit that only serve your site, plus timing. That's also the part the landlord most needs to have a view on, because it's the part that stays in their ground.

What to agree before you install anything

Get these in writing, as a lease variation or side letter, before a single trench is dug:

  • Consent to install, connect and maintain chargers, storage and the supply, and to apply for any grant that needs landlord sign-off.
  • Who owns each piece of kit during the lease and at the end, item by item: charger units, cabling, switchgear, transformer, substation.
  • Reinstatement switched off for the charging infrastructure. If the landlord wants it left in place, it shouldn't cost you to leave it.
  • What happens to its value at the end. Either the landlord pays a fair price for what you leave, or the term gets extended to match.
  • A rent review that ignores the power you paid for. If the supply is your improvement, you shouldn't pay rent on it at the next review.
  • The capacity ring-fenced for you, so the landlord can't hand your kVA to another tenant on a multi-let estate.
  • Rights for the DNO: wayleaves, easements and any substation lease, agreed early so your connection offer doesn't time out waiting for them.
  • Access for maintenance and a cable route that won't get dug up.
  • A term or option to renew that gives the kit time to pay back.
  • What happens to your connection agreement if you leave, and whether it can pass to the next tenant.

None of this is exotic. It's ordinary property work, and a good property solicitor will have seen most of it. The mistake is doing it after the chargers are in, when the landlord holds every card.

How long is left on your lease?

Over ten years left: you've got time and leverage. Negotiate the list and get on with it.

Five to ten years: it can still work, but the payback window is tight. This is where a lease extension, traded for the improvement you're bringing to the site, makes sense. Storage can buy time while a phased connection gets built. But storage with a connection date is a bridge. Storage without one is a raft.

Under five years: don't put fixed infrastructure in without an agreement on what happens at the end. Extend, or plan your first trucks around charging you don't have to own.

On a customer's site or a shared yard the same list applies, but the other party's motives are different. A customer who wants electric deliveries has a reason to help. Use it.

What should change

Tenants shouldn't have to negotiate from scratch for permission to decarbonise. California has given commercial tenants the right to install EV charging at their own cost since 2015. Our Power In report asks DfT and MHCLG to legislate for the same thing at fleet scale. Aldersgate Group and the REA have called for model lease clauses and a code of practice for landlords and tenants too.

Until that happens, the lease is the job. Landlords have worked out that power is worth money. Make sure some of that value comes back to the tenant who paid for it.